Master Plan IPC Banten

Development Plan PT. Pelabuhan Indonesia II Cab. Banten

Master Plan IPC Banten has been built gradually up to 2036 based on flow of goods progress. Port development has been built up in 3 stages.

1. Short Term Development (up to 2018)

Short term development picture, click here..

I
GENERAL
1
Reclamation
300.000 m2
2

Terminal Facilities

Dry Bulk Stock Yard

Dry Bulk Warehouse

General Cargo Stock Yard

 

50.865 m2

21.600 m2

14.500 m2

3
Reception Facilities
1.500 m2
4
Road
800 m2
5
Clean Water Installation
1 LS
II
DRY BULK BERTH
1
Berth Development
10.086 m2
2
Dredging
1 LS
III
NON DRY BURK BERTH
1
Additional Berth Length
5.700 m2

 

2. Medium Term Development (Up to 2023)

Medium term development picture, click here..

I
GENERAL
1
Reclamation
150.000 m2
2

Terminal Facilities

Dry Bulk Stock Yard

General Cargo Stock Yard

 

15.000 m2

7.000 m2

3
Road
300 m2
4
Clean Water Installastion
1 LS
II
DRY BULK BERTH
1
Berth Development
3.264 m2
2
Dredging
1 LS
III
DERMAGA CURAH KERING NON PANGAN
1
Additional Berth Length
13.500 m2

 

 

3. Long Term Development (Up to 2033)

Long term development picture, click here..

I
GENERAL
1

Terminal Facilities

Dry Bulk Stock Yard

Alternative Dry Bulk Stock Yard

 

48.000 m2

48.000 m2

2
Road
400 m2
3
Clean Water Installation
1 LS
4
Gate in
1 LS